X finishes a work 3 days earlier than Y. Y do it for 4 days then leaves, the rest
of the work was finished by X alone, thus the work was completed in 14 days
How much time X and Y each will take separately to finish it:
(a) 12 days, 14 days
(b) 14 days, 16 days
(c) 15 days, 12 days
(d) 12 days, 15 days​

Answers

Answered by maliniprincess5796
8

Step-by-step explanation:

the first line of the question is enough to solve this as the only option which satisfies that condition is option 3 x=15 and y=12 solve mcq's like this shortly