X is half as efficient as y and he is able to complete a job 50 days more than y. If they are working together how many days will it take to complete the job?
Answers
Answered by
1
Answer:
efficiency of x let = 1
than , efficiency of y = 2
efficiency = 1:2 (x:y)
time = 2:1 (x:y)
time difference = 2-1 = 1
given 1-----------50
so, 2 ------------100
Number of days by X = 100
number of days by y = 50
LCM = 100 = Total work
both do in = 100/3 = 33(1/3) days . [Ans.)