X works twice as fast as Y. If Y can complete a job alone in 12 days, then in how many days can X and Y together finish the job?
Answers
Answered by
9
x = 2y
so,
y = 12 days
x = 6 days
total unit of work = 12
for l day,
x = 2 , y= 1
so,
x+y = 2+1 = 3unit = 1day
1 unit = 1/3
12 unit = 12/3
= 4 days
Similar questions