x,y and Z can do a piece of work in 15. 12 and 30 days, respectively. They started work together, but
ter 2 days. In what time will the remaining work be completed by X and Z?
Answers
Step-by-step explanation:
answer see in the above picture
Answers :
6⅓ days
Step-by-step explanation:
X can do the work in 15 days
therefore, X's 1 day's work = 1/15 parts
Y can do the work in 12 day
therefore, Y's 1 day's work = 1/12 parts
Z can do the work in 30 day
therefore, Z's 1 day's work = 1/30 parts
(X,Y and Z)'s together work in 1 day=1/15+1/12+1/30
= 4+5+2/60
= 11/60
X,Y and Z can do the work in 2 days = 2×11/60
= 22/60
Remaining work = 1-22/60
= 60-22/60
= 38/60
= 19/30
Remaining will be completed by X and Y
X and Z can do the work in 1 day= 1/15+1/30
= 2+1/30
= 3/30
= 1/10
since, 1/10×10 => 1
therefore, X and Z can do the work in 1 day=10days
X and Z can do the work in 19/30 work in = 19/30×10
=> 19/3
=> 6⅓ Days