Math, asked by sksingh617089, 8 months ago

XERCISE 11.3
A can complete a work in 16 days, B can complete the same work in 18 days and C in 24 days. How
ong will all three of them will take to complete the work by working together?​

Answers

Answered by goldengirl21
3

Answer:

A - 16 days

A in 1 day - 1/16. work

B - 18 days

B in 1 day. -. 1/18 work

C in 24 days

C in 1 day - 1/24 work

A +B +C (together in 1 day) = 1/16 + 1/18 + 1/24

= 9+8+6 / 144

= 23/144

( flip the answer it will turn into days )

so, in 144/23 days work will be completed by them together.