Math, asked by Srushtiwadekar, 1 year ago

Yogesh requires 3days more than Vivek to do work completely .If both work together they complete work 2 days.Find number of days required to each of them to complete the work.

Answers

Answered by salusuju
2

i hope this may help you mate

Attachments:
Answered by aryankunalroy38
1

see the attachment

mark me as brainliest answer✌️

Attachments: