You are managing a project to build an urgent care clinic. Your company is expanding and has constructed 25 clinics so far. Which estimating technique makes the most sense to use in this situation?

Answers

Answered by PiaDeveau
15

Parametric modeling

Explanation:

It is a modern scientific method when studying past events to estimate data for future events. This is called parametric modeling.

In the given question, the company already has the data to build 25 clinics with the help of which it can run new projects more smoothly.

Therefore the above answer is correct.