You are targeting a total Production Volume increase of 10% in the next 7 days compared to the last 7 days' Actual Production Volume. Assuming you maintain the same Productivity Rate as last week for the next 7 days, approximately how many Scheduled Hours will you need to schedule to achieve this goal
Answers
Answered by
0
Let x = current producton rate in vol/hour.
Then the current production volume in 7 days is
V = (24*7)x = 168x
The targeted production increase is 10%, so the new weekly volume is
1.1*(168x) = 184.8x
Let y = the extra hours required to meet the new targeted volume. Therefore
(168 + y)x = 184.8x
Divide by x.
168 + y = 184.8
y = 184.8 - 168 = 16.8 hours
Answer:
For the week:
The scheduled hours is 184.8
The extra hours is 16.8
Similar questions
Social Sciences,
1 month ago
Math,
3 months ago
Biology,
3 months ago
History,
10 months ago
Physics,
10 months ago