You are using earned value analysis to track your project's progress. In your project, earned value is higher than planned value and actual value. That means the project is _____ schedule and _____ budget.
Select an answer:
behind; under
ahead of; under
ahead of: over
behind; over
Answers
Answered by
0
Answer:
behind under
surviving for sick many Jack can
Answered by
0
Answer:
You are using earned value analysis to track your project's progress. In your project, earned value is higher than planned value and actual value. That means the project is _____ schedule and _____ budget.
Answer: Ahead of; under