Business Studies, asked by to6697, 8 months ago

You are using earned value analysis to track your project's progress. In your project, earned value is higher than planned value and actual value. That means the project is _____ schedule and _____ budget.

Select an answer:

behind; under


ahead of; under


ahead of: over


behind; over

Answers

Answered by mithileshpathak7181
0

Answer:

behind under

surviving for sick many Jack can

Answered by vazpreethi
0

Answer:

You are using earned value analysis to track your project's progress. In your project, earned value is higher than planned value and actual value. That means the project is _____ schedule and _____ budget.

Answer: Ahead of; under

Explanation:

Similar questions