You are using earned value analysis to track your project's progress. In your project, earned value is higher than planned value and actual value. That means the project is _____ schedule and _____ budget.

Select an answer:

behind; under


ahead of; under


ahead of: over


behind; over

Answers

Answered by mithileshpathak7181
0

Answer:

behind under

surviving for sick many Jack can

Answered by vazpreethi
0

Answer:

You are using earned value analysis to track your project's progress. In your project, earned value is higher than planned value and actual value. That means the project is _____ schedule and _____ budget.

Answer: Ahead of; under

Explanation: