You have finished planning and have begun executing the project when the client asks if you would add some important features to the product of the project. How are the triple constraints affected?

Answers

Answered by Anonymous
8

Explanation:

Scope and quality would be affected but not cost

Cost must remain constant because resources are limited

Adding features will require additional cost but not time

Time and cost may both be affected