Business Studies, asked by TbiaSamishta, 1 year ago

You want level by task, focusing only on selected region of your project. How can this be accomplished? a) Highlight the task to level by selecting rows. b) Select resource tab level group, level resource. c) Select resource tab, level group, level tasks d) select resource tab, level group, level selection.

Answers

Answered by Arslankincsem
0

Explanation:

d) is the right option for the given question. You have to first select resource tab, level group, level selection. Here you have to select from and to date to make the changes. You can go through the realistic timeline to do the project adjustment assignments. There are also other options for the leveling control. You can do the necessary changes as per requirement.