Your company has been hired to install an automatic sprinkler system for a large park. The mechanical and non-mechanical components of the job are listed in random order below. Organize the components in the correct sequence:

a. Dig trenches to bury the water pipes
b. Set the timer for the watering times
c. Identify areas that need watering
d. Sketch a plan of the locations of water pipes and sprinkler heads
e. Connect the pipes to the water supply
f. Connect the pipes to the sprinkler heads and bury them in trenches

Answers

Answered by adityajha1734
1

Answer:

your answer is a option