Your project has a part-time resource who works 4 hours a day from Monday through Thursday: You need to ensure that your project plan accommodates the part-time resource. What should you do?

Select one:

a. Change the working time for the resource

b. Change the max units for the resource

c. Update the project calendar

d. Assign the resource only to tasks that are scheduled on the working days​

Answers

Answered by alienfighter0000
1

Answer:

A.

Change the working time for the resource.