Zeel takes 75 days to complete the job while working 20 hours a day. How many days will she require to complete job, if she works for 15 hours a day?
Answers
Answered by
8
Total hours = 75×20=1500 hours
= 75×15=1125 hours
= 1500-1125=375
= 375÷15=25
=75+25=100
Answer - So, zeel will require 100 days to complete job.