(1)
A and B can do a piece of work in 6 days and C in 12 days. In how many days
A, B and C will do it together?
Answers
Answered by
0
Answer:
1/6+1/12
2+1/12
3/12
1/4
A B and C will do it together in 4 days
Explanation:
please like my answer I hope it will help you
Answered by
0
Explanation:
I want to ask that in the Question A&B are doing the work together in 6 days or while doing solo BTW
solving if A&B are doing the work together in 6 days
part of work A&B will finish together in one day = 1/6
part of work C will finish it alone in one day = 1/12
part of work they will finish while working together in one day
= 1/6+1/12=2+1/12=3/12=1/4
so part of work they will finish while working together =1÷1/4=4
So they will take 4 days to finish the work together .
if they takes 6 days alone then you follow the steps and that's simple.