1.
How much work is done in moving a charge of 2C between two points at a potential
difference of 50 V ?
Answers
Answered by
1
Explanation:
We have to take potential difference as work done per unit charge to bring it from a point 0 to 12V. Hence, the work done in moving a charge of 2c across the two points having a potential difference is 12V is 24J.
hope this helps☺✌
keep following❤❤
Answered by
0
Explanation:
We have to take potential difference as work done per unit charge to bring it from a point 0 to 12V. Hence, the work done in moving a charge of 2c across the two points having a potential difference is 12V is 24J.