1. The Shortest Processing Time (SPT) rule
(i) Ensures that due dates are met
(ii) Maximizes average flow-time
(iii) Minimizes resource utilization
(iv) Minimizes work in process inventory
Answers
Answered by
0
Answer:
option b is the correct answer