Math, asked by zxcv1, 1 year ago

10 mechanics complete 50 jobs in 25 day ...how much worker required to complete the work in 15 days

Answers

Answered by pratibhajaiswal
0
Hi the answer is 6 worker
Answered by utsavk
0
hello the answer is 6 worker