10 men can complete a job in 14 days. How
long will it take 4 men to finish the same job if
they work? at the same rate?​

Answers

Answered by sanilsingh2345
0

Answer:

10/14=4/x

cross multiplication

10*x=14*4

x=14*4/10

x=56/10

x= 5.6