10 men or 12 women complete one job in
10 days. In how many days do 5 men and 6
women together complete the job?
1. 8 days
2. 10 days
3. 12 days
4. 15 days
Answers
Answered by
1
10 men + 12 women = 22 people
total days = 10 days
22 people take 10 days to complete the jobs
5 men + 6 women = 11 people
=5 days
Answered by
0
2. 10 days is required for 5 men and 6 women together to complete the job.
Given:
No. of men working
No. of women working
Total number of days taken by them to complete a work
As we know,
From the given information, the efficiency of a man=
The efficiency of a woman is=
Let the time taken by 5 men and 6 women be x days.
So, the efficiency of 5 men
The efficiency of 6 women
Hence, the total efficiency of 5 men and 6 women will be
So, using the formula we get,
Hence the required time will be 10 days.