10 men or 15 women can do a work in 14 days. In how many days the same work can be completed by 20 men and 5 women ?
1) 4 days 2) 6 days 3) 8 days
4) 10 days​

Answers

Answered by rk7093357
2

Answer:

I am answer ing through pic. mark me as brainlist answer

Attachments:
Answered by harendrakumar4417
1

In 6 days the same work can be completed by 20 men and 5 women.

Step-by-step explanation:

10 men or 15 women can do a work in 14 days.

10 men can do \frac{1}{14} th of a work in 1 day.

1 men can do \frac{1}{10\times14}th of a work in 1 day.

20 men can do \frac{20}{10\times 14}th of a work in 1 day.

15 women can do \frac{1}{14}th of a work in 1 day.

1 women can do \frac{1}{15\times 14}th of a work in 1 day.

5 women can do \frac{5}{15\times 14}th of a work in 1 day.

20 men and 5 women can do [\frac{20}{10\times 14} + \frac{5}{15\times 14}]th = [\frac{1}{7} + \frac{1}{42}]th = \frac{1}{6}th of a work in 1 day.

20 men and 5 women can do the same work in 6 days.

Hence, in 6 days the same work can be completed by 20 men and 5 women.