10 people could complete a task in 8 days. After 4 days 2 of the worker left. How many days from then did it take to compkete the task
Answers
Answered by
0
they can complete the work in 10 days
mfag:
wrong
Answered by
0
Answer: 5 days
Step-by-step explanation:
Let 1 people can do 1 work per day
So, 10 people can do 10 work per day
.: total work in 8 days = 10*8 = 80
Work done by 10 people in 4 days = 40
Work left = 80 - 40
Work left = 40
Out of 10 people, 2 people left the work after working together for 4 day's , so (10 - 2 = 8) 8 people can complete the remaining work.
.: No of days to complete the remaining work is = 40/8
= 5 days