Math, asked by saanvi5713, 1 year ago

10 people could complete a task in 8 days. After 4 days 2 of the worker left. How many days from then did it take to compkete the task

Answers

Answered by saiyam93
0
they can complete the work in 10 days

mfag: wrong
Answered by SUSHILPRASAD
0

Answer: 5 days

Step-by-step explanation:

Let 1 people can do 1 work per day

So, 10 people can do 10 work per day

.: total work in 8 days = 10*8 = 80

Work done by 10 people in 4 days = 40

Work left = 80 - 40

Work left = 40

Out of 10 people, 2 people left the work after working together for 4 day's , so (10 - 2 = 8) 8 people can complete the remaining work.

.: No of days to complete the remaining work is = 40/8

= 5 days