Math, asked by mvgkraju, 1 year ago

10 persons can finish a piece of work in 15 days, in how many days the same work can be done by 25 persons

Answers

Answered by avanishsingh2
2
let the work can be done by 25 persons be x days.
person ----- days
10 ------------- 15
25 ------------ x

25x = 10× 15
x = 150/25
x= 6 days
Answered by divyansh6666
5

this is your ans it will help u

Attachments:
Similar questions