10 women can do a piece of work in 20 days.If 2 of the women deny to work, then how many days are required to complete the work?
Answers
Answered by
0
Given,
10 women can do a work in 20 days.
If 2 women deny to work,then 8 women are left.
Let us take x as the no of days.
So,
10×20=8×x
200÷8=x
X=25.
Hence, the no of days taken by 8 women to complete the work will be 25 days.