10 workers finish a job in 10 days. In how many days will 20 workers finish the job? Is this a direct variation? How?
Answers
Answered by
14
10 workers finish a job in 10 days
1 worker will finsh same job in 10 × 10 = 100 days
as when numbers of workers will be reduced time taken will be increased
so its a inversely proportion
its not direct but inversely.
20 workers will take = 100/20 = 5 days
or we can do it this way
man day required to do a job =numbers of men and days required
man days required = 10 × 10 = 100 man days
let say 20 workers will take x days
then
man days required = 20x
20x = 100
=> x = 5
5 days required.