100 men working 8 hours a day can complete a job in 35 days. how many men should be employed to finish the job in 25 days if they work 10 hours a day.
Answers
Answered by
8
Answer:
#
Step-by-step explanation:
I think it helps u
I u r satisfied pls mark as brainliest
Attachments:
Answered by
0
Given: 100 men working 8 hours a day can complete a job in 35 days.
To find: We have to find the number of men required to finish the job in 25 days if they work 10 hours a day.
Solution:
To determine the number of men we have to use the below formula-
M1D1H1=M2D2H2
Where M1 is the initial number of men=100
D1 is the initial days required to complete the work=35
H1 is the initial working hours=8
M2 is the required number of men=x
D2 is the days required to complete the work=25
H2 is the working hours=10
Putting the values in the above formula we get-
Thus 112 men were required to finish the job.