(11) For doing some work Ganesh takes 10 days more than Gajanan. If both work
together, they complete the work in 12 days. Find the number of days taken by
Ganesh to complete the work, if he works alone.
Answers
Answered by
0
Answer:
30 days
Step-by-step explanation:
Steps are given in the above attachment....
PLEASE MARK THIS ANSWER AS THE BRAINLIEST ANSWER!!!!!!!
Attachments:
Answered by
1
Answer:
let the work be 1
gajanan done his work in x days.
hence ganesh take x+10 days to done the work
ganesh complete 1/x work in 1 day
gajanana complete 1/x+10 work in 1 day
by 1st condition,
12/x+12/x+10=1
12(x+10)+12(x)/x( x+10)=1
12x+120+12x/x^2+10x=1
24x+120=x2+10x
x2+10x-24x-120=0
x2-14x-120=0
x2-20x+6x-120=0
x(x-20)+6(x-20)=0
(x-20)(x+6)=0
x-20=0or x+6=0
x=20or x=-6
but work is not negative
x=20
ganesh complete work in x+10days=20+10=30
hence Ganesh complete the work in 30 days