Math, asked by Sinthiya9750, 1 year ago

11 potters can make 143 pots in 8 days. How many potters will be required to make 169 pots in 4 days?

Answers

Answered by vaaruni84
8
11 potters can make 143 pots in 8 days.

1 potter can make 143 pots in 8 × 11 days.

1 potter can make 1 pot in (8 × 11)/143 days.

Let the number of potters required be x, then;

 x potters can make 1 pot in (8 × 11)/( 143 × x) days

x potters can make 169 pots in (8 × 11 × 169)/(143 × x ) days

But the number of days given = 4

 According to the problem;

(8 × 11 × 169)/(143 × x ) = 4

14872/143x = 4

572x = 14872

x = 14872/572

x = 26

Therefore, 26 potters are required to make 169 pots in 4 days.