12 male persons and 15 female persons complete a work in 20 days. how many days it will take when 4 male persons and 5 female persons will do it? explain it plz
Answers
Answered by
1
let the no. of days taken by 4 male person and 5 female person be x
total no. of people in the first case = 12+15=27
total no. of people in the second case = 4+5=9
no. of people (p) = 27, 9
no. of days(q)= 20, x
less the people, more the no. of days taken to complete the work, hence, and q vary inversely.
p×q=27×20=9×x
540=9x
540/9=x
60=x
hence, 4 male persons and 5 female persons take 60 days to complete their work.
total no. of people in the first case = 12+15=27
total no. of people in the second case = 4+5=9
no. of people (p) = 27, 9
no. of days(q)= 20, x
less the people, more the no. of days taken to complete the work, hence, and q vary inversely.
p×q=27×20=9×x
540=9x
540/9=x
60=x
hence, 4 male persons and 5 female persons take 60 days to complete their work.
Answered by
2
Ans=40 days is our answer
hope it will help