12 men can complete a piece of work in 25 days. in how many days can 30 men complete the same piece of work
Answers
Answered by
0
Work is proportional to number of men and number of days
Work = 12 men × 25 days = 300 men days
So,
300 men days / (30 men) = 10 days
It’ll take 10 days to complete the same piece of work by 30 men