12 men can complete the work in 8 days 3 days after they started work and 3 more men joined them in how many days they can complete remaining work

Answers

Answered by JunaidMirza
4
Work = 12 men × 8 days = 96 men days

In 3 days work done = 3 days × 12 men = 36 men days

Remaining work = 96 men days - 36 men days = 60 men days

Now, we have 15 men to complete work of 60 men days

60 men days × 1 / (15 men) = 4 days

Remaining work will be done in 4 days