12 men can complete a piece of work in 36 days,18 women can complete a piece of work in 60 days.8 men and 20 women work together for 20 days
Answers
Answered by
1
Step-by-step explanation:
12 men can complete a piece of work in 36 days
=> 1 man can complete the work in 36 × 12 days (∵ less man, more days. inversely proportional)
=> Work done by 1 man in 1 day =
1/36*12
18 women can complete the same piece of work in 60 days
=> 1 woman can complete the work in 60 × 18 days
=> Work done by 1 woman in 1 day =
1/60*18
Work done by 8 men and 20 women in 1 day =
18/36*12 + 20/60*18 + = 1/54+1/54= 1/27
=
Work done by 8 men and 20 women in 20 days = 20/27
Remaining work =
1-20/27= 7/27
Let n women complete this work in 4 days. Then
1/60*18 *n* 4= 7/27
n/15*18= 7/27
n= 15*18*7/27
n=5
Required number of women to complete the remaining work = 70