12 men can do a piece of work in 16 days then 8 men will take how many days
Answers
Answered by
1
Answer:
24days
Step-by-step explanation:
12 men can do work in 16 days so 1 men will do a work in 12 × 16 days. so 8 men will take (12 × 16 )÷ 2 = 24 days