Math, asked by garryrandhawa, 11 months ago

12 men can do a piece of work in 24 days in how many days will the work be completed if 8 men are engaged to do this work​

Answers

Answered by elysian94
8

Answer:

Let they will take x days.

12 : 24 = 8 : x

Using rule of inverse proportion.

8 * x = 12 * 24

Or, x = 12 * 3 = 36.

Thus, 8 men will take 36 days.

_______________❎"

Similar questions