12 men can do a piece of work in 24 days in how many days will the work be completed if 8 men are engaged to do this work
Answers
Answered by
8
Answer:
Let they will take x days.
12 : 24 = 8 : x
Using rule of inverse proportion.
8 * x = 12 * 24
Or, x = 12 * 3 = 36.
Thus, 8 men will take 36 days.