12 men can do a work in 18 days. 4 days after they started the work 8 more men joined them.how many days will it take them now to complete the remaining work
Answers
Answered by
0
Answer:
Step-by-step explanation:
12man can-do in one day=1/18part
4days they have done=4*1/18=2/9
Remaining work=1-2/9=7/9
One man can do=1/18*1/12=1/216
20man do=20/216=5/54
Remaining job completed in=7/9*54/5=42/5days