12 men can do a work in 24 days then in how mny days 18 men can do the same work
Answers
Answered by
0
Answer:
The 18 men can do the work in 16 days..
Step-by-step explanation:
because-
If 12 men can do the work in 24 days ,
Then,18 men will do the same work less than 24
days.
so,
let the no.of days be x,
12/18 =x/24
18x=12*24
x=12*24/18
x = 16 days
Hope it helps!!!!