12 men can do work in 30 days .the time taken to complete the work by 20 men is
Answers
Answered by
1
Answer:
48days
Step-by-step explanation:
1 man will complete the job in 16×12 days.
So, 4 will do in
4
12×16
=48 days.
Answered by
1
Answer:
18 days
Step-by-step explanation:
1man can do work in 30×12 = 360 days
20 men can do work in 360÷20 = 18 days