12 men complete a work in 18 days six days after i had started working for men join them how many more days will of them take a complete the remaining work
Answers
Answered by
1
Answer:
12 MENS COMPLETE WORK = 18 DAYS
TOTAL WORK ==> 12*18 ==> 216
===> SIX DAYS ==> 12*6 ==> 72
SO, 216-72 ==> 144
SO, AFTER 6 DAYS ==> 12+1 ==> 13
SO, ANSWER ==> 144/13
Answered by
0
Let the work completed by 1 man in 1 day be y.
So, the total work = 12 X 18 X y = 216y
12 men worked for 6 days, so total work
completed = 12 X 6 X y = 72y
Remaining work = 144y
Total men now = 12 + 4 = 16
Work done in a day = 16y
Days required = Total work/Work in a day
= 144y/16y
= 9days
HOPE IT HELPS