Math, asked by KirveAtharav, 1 year ago

12 men or 24 women can do 1 work in 24 days .If 8 men and 8 women work together how many days it will take to complete the work?​

Answers

Answered by aniketprasad123
2

Answer: 24 Days

Step-by-step explanation

12 men are able to do 1 work in 24 days

24 women are able to 1 work in 24 days

so , number of women /number of men

   = 24/12

   = 2/1

which means 1 man = 2 women

hence,

           require day to complete work = (number of men)+(number of                  women)

                                                              = (8×2)+8

                                                              = 24

so,

     8 men and 8 women can do 1 work in 24 days