12 men working at 6hr day can do apiece of work in 14 days. How workers can complete the same work in 8 days working 7 hrs. Per day.

Answers

Answered by rahman786khalilu
26

Given

12 men working 6 hr day work in 14 days

X men working 7hr day work in 8 days

no of men is inversely proportional to the no of hours and also inversely proportional to no of days

12/x = 7 : 6 :: 8 : 14

12/x = 7 x 8 /6 x14

12/x = 4/6

x= 12 x 6 /4

x= 3x 6 = 18

Therefore 18 Men required to complete the work in 8days working 7hrs per day

mark as brainliest answer

Answered by hiteshkumarpalai
3

Answer:

12 ×6=72

14×72=1008

8×7=56

1008/56

18 days