12 people need 45 days to complete a work how many days is needed for 27 workers to do a work
Answers
Answered by
2
Answer:
20
Step-by-step explanation:
Let the total work be considered as unity.
So, in 45 days, 12 people do unity work
In 1 day, work done by 12 people = 1/45
In 1 day, work done by 1 person = 1/540
In 1 day, work done by 27 people = 27/540 = 1/20
So, to complete the work, 27 people will require 20 days.
A short trick used by me:-
When this type of problems are faced, remember that the product of no. of men and no. of days = constant.
Let the no. of days req. = x
So, 45 * 12 = 27 * x
So, x = 45*12/27 = 20.
This proved to be helpful for me.