Math, asked by twitter3848, 1 year ago

12 persons completed a job in 15 days how many days will 20 persons take to complete the job

Answers

Answered by Anonymous
1
HEY Buddy....!! here is ur answer

Answer : 9 days

Given that : 12 persons complete a job in 15 days then,

1 person can complete the job = 15×12 = 180 days

Now 20 persons can complete the job = 180/20 = 9 days

So, 20 persons complete a job in 9 days.

I hope it will be helpful for you...!!

THANK YOU ✌️✌️