12 persons take 9 days to prepare 18 windows.The no of days required by 54 persons to prepare 45 windows.
Answers
Answered by
0
It is given that , 12 persons take 9 days to prepare 18 windows.
12 Persons →9 Days →18 windows
As number of persons increases number of Days Decreases or vice versa.
Let, number of days required by 54 persons to prepare 45 windows= x days
So, Expressing the following in terms of proportionality and equating:
→ →→→Dividing both sides by 6
So, number of days required by 54 persons to prepare 45 windows= 20 days