Math, asked by livancekujur6, 9 months ago

12 workers can do a piece of work in 36 days,in how many days 18 workers can finish​

Answers

Answered by shruti3148
0

Answer:

18 workers can finish the work in 24 days.

Step-by-step explanation:

Apply inverse variation method for this sum. It's the easiest method.

Answered by surajkumar271267
1

Answer:

12 workers can do a peice of work in 36 days.

1 worker can do that work in 36 ×12

therefore

18 workers can do it in days=( 36×12)÷18

=24...days

Hope it helps you

Mark me as brainliest