Math, asked by rahulb247, 11 months ago

12 workers finish job in 20 hrs how many workers will be required to finish the same job in 15 hrs

Answers

Answered by ifraajmal163
17

Step-by-step explanation:

12 workers takes =20hrs

12×20worker will take =1hr. (indirect relation). because 1 worker will take more time to do that work

15 hrs will be taken by (more worker will take less time ,, that's why we divided)

12×20/15

=16workers

Answered by Sunainaaa
6

Answer:

Step-by-step explanation: