120 men can do a work for 100days. than 150 men will do
Answers
Answered by
8
120 men can do a work in 100 days
therefore..150 men will do the work in
Answered by
1
Answer:
80 Days
Explanation:
120 men can do a work for 100days
i.e 1 man can do a work for 100*120
so, 150 mens will do this work in 100*120/150 = 80 days