13 men can weave 117 baskets in a week. How many men will be needed to weave 189 baskets in 3 days
Answers
Answered by
1
78 is the the correct answer for this
Answered by
3
Step-by-step explanation:
13 men can weave 117 baskets in a week, so how many men will be required to weave 189 baskets in 3 days??
Let the work done by each men per day be x.
Since 13 men can weave 117 baskets in a week. So,
So let the number of men required to weave 189 baskets in 3 days be y. So,
So number of men required is 49.