Math, asked by gayatrikulkarni1111, 6 months ago

13. Mr. Sachin, a civil engineer undertook the construction of a multi storied hotel
to be completed in 140 days. He employed 180 laborers to complete it, At the
end of 76 days, only half of the work was done, so he hired 10 extra laborers and
completed the work. By how many days did he exceed the specified time? *
8 days
12.5 days
6 days
3days​

Answers

Answered by amitnrw
0

Given : Mr. Sachin, a civil engineer undertook the construction of a multi storied hotel  to be completed in 140 days. He employed 180 laborers to complete it, At the  end of 76 days, only half of the work was done, so he hired 10 extra laborers and  completed the work

To Find :   By how many days did he exceed the specified time

Solution:

180 Labors did work for 76 Days

Work done = 180 * 76 man days

it was half of the Work

so work Left =  180 * 76 man days

Now workers  = 180 + 10 = 190

More days required =  180 * 76  / 190

= 72

Total Days = 76 + 72 = 148

Work exceed by 148 - 140 = 8 Days

by 8 days he exceed the specified time

Learn More:

12 men complete a work in 9 days after they worked for 6 days 6 ...

https://brainly.in/question/11630708

with P starting the work, working on alternate days P and Q can ...

https://brainly.in/question/12303996

Similar questions