14 men can do a piece of work in 11 days working 8 hours a day.in how many days will 22 men finish the same work working 7 hours a day
Answers
Answered by
113
8 days
Step-by-step explanation:
More men, more work efficiency
More work efficiency, less days. (indirect)
14 men working 8 hours a day complete the work in 11 days
1 men working 8 hours a day complete the work in 11 × 14 days
1 men working 1 hour a day complete the work in 11 × 14 × 8 days
22 men finish the same work in 11 × 14 × 8 ÷ 22 days
22 men working 7 hours a day finish the same work in
Answered by
75
Given :-
14 men can do a piece of work in 11 days working 8 hours a day
To Find :-
How many days will 22 men finish the same work working 7 hours a day
Solution :-
14 men can do a piece of work in 11 days working 8 hours a day
1 men can do a piece of work if he do for 1 hour = 14 × 11 × 8 = 1232 days
22 men finish the same work working 7 hours a day = x
x = 1232/22 × 7
x = 56/7
x = 8