14 men can do a work in 8 days.In how many days will 28 men finish the same work?
vedasrireddy:
This question is from direct and inverse proportions chapter class 8
Answers
Answered by
17
4 days.
In the question Given
14 men can do a work in 8 days.
Here we Find in the questions.
how many days will 28 men finish the same work?
Solution .
Here , using alternate methods
14 men can do a work in 8 days.
1 man can doing same work 14 × 8 = 112
28 man doing same work equal to
Therefore 28 men finish the same work in 4 day.
Be brainly
Answered by
35
Here , using alternate methods
14 men can do a work in 8 days.
Therefore 28 men finish the same work in 4 day.